Walk past the gate at the end of Cascade Drive this month and look for the new bridge over San Anselmo Creek. Where is it? It isn't at the entrance. Marin County Parks finished the upper Cascade Canyon bridge, which the project calls Bridge 2, on October 12, 2026. The lower bridge, Bridge 1, is the one closest to the trailhead, and it is scheduled for August through October 2027.
That order follows from a rule that runs through nearly every project in the hills above town right now. Each one works inside a seasonal window set by what lives there. In the canyon, the window is the creek's dry months, and it has already closed. On the Mt. Tam Watershed, the window is set by a nesting owl and runs to the end of January. Along Bolinas Road, the pipeline work is on hold until 2027. So this winter, residents get the in-between version of all three.
Bridge 2 Went In Upstream
The county's environmental document for the project spells out both sites. The CEQA initial study describes what you meet, in order, when you head in from the Cascade Drive gate:
- The future Bridge 1 site, near the entrance to Cascade Canyon Fire Road, at the downstream end of a meander bend. The plan calls for a 90-foot span in two or three sections, set 140 feet downstream of the first of the canyon's four low-water rock fords.
- The new Bridge 2, about 1,000 feet upstream of that site: a 60-foot crossing built from two prefabricated sections, next to an existing rock ford.
The county's own assessment says Bridge 2 can be seen from Cascade Canyon Fire Road and from the trail to Cascade Falls. Neither bridge can be seen from private homes or public roads. The new steel is a canyon-floor feature, so you won't spot it driving up Cascade Drive. The creek it spans runs 30 to 50 feet wide and sits well below the flat canyon floor.
The rock fords aren't going away. The design keeps them for Marin County Open Space District crews and emergency vehicles. Split-rail fencing and signage along the old approaches steer visitors to the bridges, and detachable rails let ranger trucks through.
Why the Work Stops When the Rain Starts
The fords were the reason for the project, and the creek's seasons set its schedule. The project page says visitors crossing on the four rock fords risk injury when the creek runs high in the rainy season. Foot and bike traffic through the channel also stirs up fine sediment that can harm federally listed steelhead downstream and block young fish moving upstream to summer habitat. Foothill yellow-legged frogs live in the same water.
Building the fix means using the same crossings. Excavators, trucks and compactors have to ford San Anselmo Creek during the dry season to reach the bridge sites. That is why each bridge gets its own late-summer window, a year apart. When the June notice went out, the Town of Fairfax told residents to expect weekday closures of Cascade Fire Road and the Highwater Trail from 8 a.m. to 4 p.m. during construction, with Canyon Trail and the Carey Camp Loop Trail kept open. That window has closed. The county marked the upper bridge complete in October, right as the rains it was built for were due.
The rainy season is also when the canyon is at its best. Marin County Parks' rangers put it plainly on the Cascade Canyon Preserve page:
Cascade Falls drops 20 feet. Visit when it's running strong in rainy season.
The same page's naturalist notes point to mushrooms and ferns in winter. They also say some parts of the preserve have seasonal night closures to protect sensitive wildlife. The county's standing rules apply on the way to the falls. Stay on roads and trails and out of the creeks, and expect mud. Dogs stay leashed, on a leash no longer than 6 feet. Electric bicycles aren't allowed. Bikes keep to 15 mph or less and slow to 5 mph when passing or at blind turns. Parking is street-only on Cascade Drive and Canyon Road. When Cascade Drive fills up, the county points visitors to an alternate trailhead at the end of Canyon Road.
Up on the Watershed, the Owl Keeps a Longer Window
Cascade Canyon connects to the Mt. Tamalpais Watershed, and the same principle runs on a different calendar up there. Marin Water is building a pair of seismically resilient, 2-million-gallon concrete tanks near Concrete Pipe and Sky Oaks roads. They will be called the Gibson Tanks, after former board member Jack Gibson, and they will eventually replace the Pine Mountain Tunnel for water storage and add capacity for Ross Valley.
The Pine Mountain Tanks project page says the construction window usually runs from August 1 to January 31 to protect the Northern Spotted Owl. That is three months longer than the creek allows in the canyon, and it reaches into the wet season. Marin Water's October 2026 update calls this the fourth straight year of construction. Crews will pour the concrete foundations for both tanks through January 31, 2027.
For anyone heading out of Fairfax toward Bon Tempe on foot or by bike, here is what that means through January 31:
- Concrete Pipe Road between Bolinas Road and Taylor Trail is closed during normal working hours.
- Bon Tempe and Bullfrog roads have intermittent closures while trucks haul material.
- Project signage on the watershed governs, and Marin Water posts a closures map on the project page.
Under the owl window, those closures follow the season. The schedule runs the whole project to winter 2029, so this pattern of late-summer starts and end-of-January stops will repeat for several more years.
Bolinas Road Clears Before December
The same pause reaches downtown, at the bottom of the route to the canyon. Marin Water's Bolinas Road pipeline replacement has been on hold since June 2026. In its October 19 construction update, the Town said crews were restoring the trench near Porteous Avenue that week so the steel plates could come off the road before winter, and patching the small squares cut along the pipeline route. The full project is expected to resume sometime in 2027.
That same update said Ross Valley Sanitary District would spend about two weeks replacing its temporary patch on Broadway between Pacheco Avenue and Bolinas Road with a permanent one. The Town noted this is spot restoration, not a full repaving, and final restoration will come later along with the district's remaining Broadway work.
That leaves Bolinas Road and Broadway clear for the four weeks when downtown hosts most of its season:
- Friday, November 20, 5 to 8 p.m.: Shop Local, Shop Late runs across downtown Fairfax.
- December 3 to 5: Mac's at 19 Broadway has Redwood Nights open-mic storytelling on Thursday, an Afro Funk Dance Party on Friday and Dirty Cello on Saturday.
- Thursday, December 10, 4:30 to 6:30 p.m.: The Fairfax Chanukah Festival takes over Bolinas Park with Saul Kaye, food and children's crafts, and the grand menorah lighting is at 6 p.m. The Pavilion is the rain venue.
- Saturday, December 12, from 5 p.m.: The Fairfax Winter Market fills Bolinas Road, starting at Broadway, with live music, local shops, performances and kids' activities.
- Sunday, December 13, 10 a.m. to 4 p.m.: The Town's Holiday Craft Faire at Fairfax Pavilion on Elsie Lane brings more than 45 vendors, plus food, music, crafts and wreathmaking.
- Wednesday, December 16, 5 to 7 p.m.: Dungeons & Dragons at the Fairfax Library, 2097 Sir Francis Drake Boulevard.
The Winter Market and the Craft Faire fall on the same weekend, a short walk apart along Bolinas Road and Elsie Lane. Cascade Drive starts at the stop sign just up Bolinas Road.
What Next Fall Finishes
When the dry-season window opens again in August 2027, Bridge 1 is due at the canyon entrance, and the county expects all of the work done by October 2027. The finished project includes trail realignments that lead to both bridges, new signage and fencing, bike speed-control features and a bike rack. It also takes out two pieces of the current trail network. The Highwater Trail, which the county describes as a narrow footpath on a steep wooded slope, will be retired and restored. So will the short Canyon Trail spur that links to Cascade Fire Road. The county's stated goal is safe, year-round access to Canyon Fire Road and the interior of the preserve without anyone having to ford San Anselmo Creek. The upper crossing has its bridge this winter. The crossing nearest the Cascade Drive gate is next on the list.
Infrastructure on these schedules shapes how a Fairfax address works through the year, from which roads are clear in December to which trailheads change before next fall. It belongs in any conversation about a home here. To talk through how the canyon, the watershed and downtown fit your own plans, Stephanie Lamarre offers a private consultation and confidential home valuation.